Dust control retrofit at an aggregate crushing plant

Three pulse-jet collectors and local capture hoods installed at the crusher discharge, screening deck and conveyor transfer points to bring the site inside local emission limits.

Country
Indonesia
Sector
Environmental Protection
Year
2023
Environmental Protection · Indonesia · 2023

The challenge

Visible dust plumes at the crusher discharge and screening deck had produced complaints from neighbouring properties and a regulatory notice. Any solution had to work without shutting the plant for more than a two-day window.

The solution

We surveyed each emission point and designed local hoods rather than attempting to ventilate the whole building. Three collectors were positioned close to their capture points to keep duct runs short. Installation was sequenced plant-by-plant so crushing continued throughout.

Results

  • Visible emissions at the three worst points eliminated
  • Site passed the follow-up regulatory inspection
  • No production lost - installation done in three staged windows
  • Filter access arranged above walkway level for safe bag changes

Equipment supplied

KZ-DC2000 pulse-jet dust collectors with local capture hoods and ducting

## The challenge

Visible dust plumes at the crusher discharge and screening deck had produced complaints from neighbouring properties and a regulatory notice. Any solution had to work without shutting the plant for more than a two-day window.

## The solution

We surveyed each emission point and designed local hoods rather than attempting to ventilate the whole building. Three collectors were positioned close to their capture points to keep duct runs short. Installation was sequenced plant-by-plant so crushing continued throughout.

Related projects

Other installations

Construction and demolition waste recycling yard Environmental Protection
Chile · 2025

Construction and demolition waste recycling yard

A 50 t/h sorting and processing line that turns demolition arisings into recycled aggregate for sub-base work, diverting material from landfill.

WhatsApp